1. Contract Number: CZ21-0741-23-A3-G2 (GMP No. 2)
2. Project Name: Gompers Preparatory Academy – NCB & Site Improvements (LLB)
3. Project Estimate: is between $32,000,000 - $36,000,000
4. Schedule: The anticipated schedule is October 2024 through August 2026
5. Project Description: The scope of work includes two new buildings (lab & classroom building 21 and lecture hall), removal of seven existing portable classroom buildings, demolition, and hazmat abatement of existing building 1, and site improvements that include a new quad, tennis courts, and walkway canopy.
  
  
  
  
collapse Document Types : Bid Documents ‎(2)
AD_Gompers Academy CS GMP 2_Final.pdf
  
9/17/2024 5:18 PMAvila II Edmundo
Final Results_Gompers CS GMP 2.pdf
  
9/17/2024 5:18 PMAvila II Edmundo
collapse Document Types : General Contractor Pre-Job Conference Form ‎(1)
Sundt Construction Pre-Job Form.pdf
  
11/15/2024 8:11 AMAvila II Edmundo
collapse Document Types : Letters of Assent (LOA) & Pre-Job Forms (PJCF) ‎(114)
Able Steel Fabricators LOA.pdf
  
3/27/2025 1:40 PMAvila II Edmundo
Able Steel Fabricators Pre-Job Form.pdf
  
4/3/2025 10:12 AMAvila II Edmundo
Ace Concrete Cutting LOA.pdf
  
11/1/2024 2:13 PMAvila II Edmundo
Ace Concrete Cutting tier to AMG Demolition Pre-Job form.pdf
  
11/1/2024 2:14 PMAvila II Edmundo
Ace Equipment LOA.pdf
  
3/25/2025 5:20 PMAvila II Edmundo
Ace Equipment tier to McKinley Pre-Job Form.pdf
  
3/28/2025 3:47 PMAvila II Edmundo
ACH Mechanical LOA.pdf
  
9/17/2024 5:19 PMAvila II Edmundo
ACH Mechanical Pre-Job form.pdf
  
11/1/2024 1:10 PMAvila II Edmundo
Advance Plumbing LOA.pdf
  
9/17/2024 5:20 PMAvila II Edmundo
Advance Plumbing Pre-Job Form.pdf
  
9/23/2024 2:01 PMAvila II Edmundo
AMG Demolition LOA.pdf
  
11/13/2024 10:46 AMAvila II Edmundo
AMG Demolition Pre-Job form.pdf
  
11/13/2024 10:46 AMAvila II Edmundo
Angelus Waterproofing LOA.pdf
  
9/23/2024 9:09 AMAvila II Edmundo
Anning-Johnson LOA.pdf
  
4/3/2025 7:29 AMAvila II Edmundo
Asbury Steel LOA.pdf
  
3/12/2025 10:49 AMAvila II Edmundo
Asbury Steel tier to Able Steel Pre-Job Form.pdf
  
3/17/2025 12:45 PMAvila II Edmundo
Baker Electric LOA.pdf
  
3/19/2025 1:52 PMAvila II Edmundo
Bielski Specialty Services LOA.pdf
  
10/28/2024 5:58 PMAvila II Edmundo
Bielski Specialty Services Pre-Job form.pdf
  
10/28/2024 5:59 PMAvila II Edmundo
Bobs Crane LOA.pdf
  
11/18/2024 12:48 PMAvila II Edmundo
Bobs Crane tier to ACH Mechanical Pre-Job Form.pdf
  
11/19/2024 11:51 AMAvila II Edmundo
Brady West LOA.pdf
  
9/18/2024 6:38 PMAvila II Edmundo
Brady West Pre-Job form.pdf
  
11/19/2024 11:48 AMAvila II Edmundo
Bragg Crane LOA.pdf
  
3/17/2025 2:31 PMAvila II Edmundo
BWE LOA.pdf
  
9/17/2024 5:20 PMAvila II Edmundo
BWE Pre-Job Form.pdf
  
9/23/2024 2:07 PMAvila II Edmundo
Cable Pipe and Leak Detection LOA.pdf
  
10/29/2024 9:44 AMAvila II Edmundo
Cable Pipe and Leak Detection tier to AMG Demo Pre-Job Form.pdf
  
11/14/2024 9:59 AMAvila II Edmundo
Cable Pipe and Leak Detection tier to FJ Willert Pre-Job form.pdf
  
10/29/2024 10:38 AMAvila II Edmundo
California Sheet Metal LOA.pdf
  
9/17/2024 5:20 PMAvila II Edmundo
Centex Glazing LOA.pdf
  
9/17/2024 5:21 PMAvila II Edmundo
Centex Glazing Pre-Job Form.pdf
  
2/12/2025 5:26 PMAvila II Edmundo
Christian Brothers Flooring LOA.pdf
  
2/12/2025 8:38 AMAvila II Edmundo
Christian Brothers Flooring Pre-Job Form.pdf
  
1/17/2025 1:25 PMAvila II Edmundo
Continental Marble and Tile LOA.pdf
  
9/17/2024 5:21 PMAvila II Edmundo
Continental Marble and Tile Pre-Job form.pdf
  
10/3/2024 3:27 PMAvila II Edmundo
Cosco Fire Protection LOA.pdf
  
9/25/2024 1:01 PMAvila II Edmundo
Cosco Fire Protection Pre-Job form.pdf
  
9/25/2024 1:01 PMAvila II Edmundo
D3 Construction Services Pre-Job Form.pdf
  
9/23/2024 2:10 PMAvila II Edmundo
Farwest Insulation LOA.pdf
  
9/17/2024 5:21 PMAvila II Edmundo
Farwest Insulation tier to Advance Plumbing Pre-Job form.pdf
  
9/23/2024 1:55 PMAvila II Edmundo
FenceCorp LOA.pdf
  
9/26/2024 11:12 AMAvila II Edmundo
FenceCorp Pre-Job form.pdf
  
12/3/2024 10:51 AMAvila II Edmundo
Ferandell Tennis Courts LOA.pdf
  
4/3/2025 7:23 AMAvila II Edmundo
Ferandell Tennis Courts Pre-Job Form.pdf
  
4/1/2025 8:59 AMAvila II Edmundo
FJ Willert LOA.pdf
  
9/17/2024 5:22 PMAvila II Edmundo
FJ Willert Pre-Job form.pdf
  
10/29/2024 9:41 AMAvila II Edmundo
Green Vista Landscape LOA.pdf
  
3/28/2025 2:18 PMAvila II Edmundo
Green Vista Landscape Pre-Job Form.pdf
  
3/12/2025 12:25 PMAvila II Edmundo
H2i Group LOA.pdf
  
3/24/2025 3:23 PMAvila II Edmundo
H2i Group Pre-Job form.pdf
  
10/17/2024 9:26 AMAvila II Edmundo
Haldeman-Homme Inc LOA.pdf
  
11/1/2024 11:09 AMAvila II Edmundo
Haldeman-Homme Inc tier to H2i Pre-Job form.pdf
  
11/4/2024 9:21 AMAvila II Edmundo
J and B Engineers Surveyors LOA.pdf
  
9/17/2024 5:22 PMAvila II Edmundo
J and B Engineers Surveyors tier to Advance Plumbing Pre-Job form.pdf
  
9/23/2024 1:51 PMAvila II Edmundo
J Corporation LOA.pdf
  
3/27/2025 11:32 AMAvila II Edmundo
J Corporation tier to Sierra School Equipment Pre-Job Form.pdf
  
4/4/2025 10:04 AMAvila II Edmundo
JDS LOA.pdf
  
11/13/2024 11:53 AMAvila II Edmundo
JDS Plumbing tier to National Electric Works Pre-Job Form.pdf
  
11/14/2024 12:14 PMAvila II Edmundo
Johnson Controls Fire LOA.pdf
  
11/13/2024 10:38 AMAvila II Edmundo
Johnson Controls Fire tier to National Electric Works Pre-Job form.pdf
  
11/13/2024 9:42 AMAvila II Edmundo
Marina Landscape LOA.pdf
  
9/18/2024 1:15 PMAvila II Edmundo
Marina Landscape Pre-Job Form.pdf
  
3/28/2025 3:44 PMAvila II Edmundo
Marina Landscape REVISED Pre-Job Form.pdf
  
4/10/2025 4:28 PMAvila II Edmundo
McKinley Elevator Corporation Pre-Job Form.pdf
  
3/24/2025 11:15 AMAvila II Edmundo
McKinley Elevator LOA.pdf
  
3/21/2025 11:11 AMAvila II Edmundo
MEK Enterprises LOA.pdf
  
3/19/2025 7:28 AMAvila II Edmundo
MEK Enterprises Pre-Job Form.pdf
  
3/26/2025 2:17 PMAvila II Edmundo
Merli Concrete Pumping LOA.pdf
  
10/21/2024 10:22 AMAvila II Edmundo
Merli Concrete Pumping tier to RCB Pre-Job Form.pdf
  
10/21/2024 10:23 AMAvila II Edmundo
MGM Contracting LOA.pdf
  
11/8/2024 11:27 AMAvila II Edmundo
MGM Contracting tier to AMG Demo Pre-Job form.pdf
  
11/13/2024 11:17 AMAvila II Edmundo
National Electric Works LOA.pdf
  
11/13/2024 11:47 AMAvila II Edmundo
National Electric Works Pre-Job Form.pdf
  
11/14/2024 9:50 AMAvila II Edmundo
P and E Insulation LOA.pdf
  
3/25/2025 10:26 AMAvila II Edmundo
P and E Insulation tier to ACH Mech Pre-Job Form.pdf
  
3/20/2025 2:52 PMAvila II Edmundo
Penn Air LOA.pdf
  
11/1/2024 2:27 PMAvila II Edmundo
Penn Air tier to ACH Mechanical Pre-Job form.pdf
  
11/4/2024 4:27 PMAvila II Edmundo
Performance Contracting LOA.pdf
  
12/30/2024 9:49 AMAvila II Edmundo
Performance Contracting Pre-Job Form.pdf
  
3/28/2025 3:53 PMAvila II Edmundo
Performance Contracting REVISED Pre-Job Form.pdf
  
4/7/2025 4:27 PMAvila II Edmundo
Phoenix Cleaning LOA.pdf
  
9/17/2024 5:22 PMAvila II Edmundo
Phoenix Cleaning Pre-Job form.pdf
  
10/17/2024 9:27 AMAvila II Edmundo
Quality Rebar tier to RCB Pre-Job Form.pdf
  
10/17/2024 9:29 AMAvila II Edmundo
Robinson Electric LOA.pdf
  
4/1/2025 10:19 AMAvila II Edmundo
Robinson Electric tier to Russell Sigler Pre-Job Form.pdf
  
4/2/2025 8:33 AMAvila II Edmundo
Rocky Coast Builders LOA.pdf
  
9/17/2024 5:22 PMAvila II Edmundo
Rocky Coast Builders Pre-Job form.pdf
  
10/31/2024 9:55 AMAvila II Edmundo
Rocky Coast Builders REVISED Pre-Job form.pdf
  
11/15/2024 11:35 AMAvila II Edmundo
Roof Construction LOA.pdf
  
9/17/2024 5:23 PMAvila II Edmundo
Roof Construction Pre-Job Form.pdf
  
10/17/2024 9:48 AMAvila II Edmundo
Russell Sigler LOA.pdf
  
3/19/2025 2:00 PMAvila II Edmundo
Russell Sigler Tier to ACH Mechanical Pre-Job Form.pdf
  
3/19/2025 1:22 PMAvila II Edmundo
San Diego Concrete Pumping LOA.pdf
  
11/4/2024 12:00 PMAvila II Edmundo
San Diego Concrete Pumping tier to RCB Pre-Job Form.pdf
  
11/8/2024 1:55 PMAvila II Edmundo
San Diego Paint Pros LOA.pdf
  
9/17/2024 5:23 PMAvila II Edmundo
San Diego Paint Pros Pre-Job Form.pdf
  
3/17/2025 12:09 PMAvila II Edmundo
Sierra School Equipment LOA.pdf
  
3/31/2025 8:42 AMAvila II Edmundo
Sierra School Equipment Pre-Job Form.pdf
  
3/27/2025 11:08 AMAvila II Edmundo
Sign Age Identity Systems LOA.pdf
  
9/17/2024 5:23 PMAvila II Edmundo
Sign Age Identity Systems Pre-Job Form.pdf
  
2/12/2025 9:39 AMAvila II Edmundo
Southland Electric LOA.pdf
  
11/13/2024 3:53 PMAvila II Edmundo
Southland Electric tier to Johnson Controls Pre-Job form.pdf
  
11/13/2024 12:24 PMAvila II Edmundo
Spooners Woodworks LOA.pdf
  
9/17/2024 5:23 PMAvila II Edmundo
Spooners Woodworks Pre-Job Form.pdf
  
3/24/2025 1:44 PMAvila II Edmundo
Star Hardware Pre-Job Form.pdf
  
10/17/2024 1:59 PMAvila II Edmundo
Ustupski's Custom Millwork LOA.pdf
  
3/27/2025 8:21 AMAvila II Edmundo
Ustupski's Custom Millwork Pre-Job Form.pdf
  
3/27/2025 11:05 AMAvila II Edmundo
Veterans Engineering LOA.pdf
  
10/30/2024 11:01 AMAvila II Edmundo
Veterans Engineering Pre-Job form.pdf
  
10/30/2024 11:01 AMAvila II Edmundo
Winegardner Masonry LOA.pdf
  
11/8/2024 12:37 PMAvila II Edmundo
Winegardner Masonry Pre-Job form.pdf
  
11/7/2024 5:04 PMAvila II Edmundo
World Bridge Technologies LOA.pdf
  
11/13/2024 5:17 PMAvila II Edmundo
World Bridge Technologies tier to National Electric Pre-Job Form.pdf
  
11/14/2024 10:37 AMAvila II Edmundo
collapse Document Types : Pre-Job Conf. (PJC) Meetings ‎(2)
2024-1-15 PJCM No.01 Gompers Preparatory Academy New Classrm Bldg_Site Improve GMP2 (CZ21-0741-23-A3-G2), Sundt_Recording.mp4
  
11/15/2024 2:19 PMWalden Loretta
2024-1-15 PJCM No.01 Gompers Preparatory Academy New Classrm Bldg_Site Improve GMP2 (CZ21-0741-23-A3-G2), Sundt_Transcript.pdf
  
11/15/2024 2:24 PMWalden Loretta